Experience gained after four weeks test pilot at Schmelzmetall Deutschland GmbH |
|
26.05.2010, 11:40 |
|
Already after four weeks of testing the machine-data system "Machine track" a first optimization potential in the Schmelzmetall Deutschland GmbH can be recognized. At the turning machines a reduction of 12% of setup time can be saved. In the planned work time of two shifts this means an increase of the availability of approximately 10 hours per week.
Another potential result is in the cleaning times. Here's a savings of 15-20% expected, about 12-20 hours per week.
The pilot test will be completed in mid-June and then evaluated the results.
|